Reservoir Woods – NATIONAL GRID NORTHEAST HEADQUARTERS
40 Sylvan Road
and
VERIZON TECHNOLOGY INNOVATION CENTER
Waltham, Massachusetts
Class ‘AA’ Corporate Headquarter Office Campus – phased new construction at former VERIZON Property
Project: This 312,000 square foot three story headquarters building meeting achieved LEED GOLD Certification as to energy conservation requirements and a supporting new 420 space parking structure is part of an overall new corporate campus development.
​
GDHarley-Services: GDHarley & Associates represented the equity investor – Prudential Real Estate Investors, working with its local Developer Partners / Davis Marcus Partners providing due diligence services and review of the proposed architectural designs prior to the loan closing; during following construction phase we provided monthly construction inspections, attendance at selected construction coordination meetings, review of monthly DRAW Package and project close-out reviews.
This property is the former GTE Sylvania Verizon Facility located on 54 Acres of wooded land in Waltham, Massachusetts (just west of Boston). It is located within the mid-portion of Boston’s Route 128 Technology Corridor and the campus faces the Cambridge Reservoir.
This new headquarters building was the 1st LEED Platinum Certified Core and Steel building in the Commonwealth of Massachusetts and is now occupied by National Grid USA Service Company, Inc. As part of National Grid’s energy conserving policies related to its electric and natural gas services and products, NATIONAL GRID added solar electric producing (photovoltaic) panels on the building’s roof and solar shading louvers on the south facing facades. All roof rain water is stored in a large storage tank under the building for use in landscape irrigation and ‘grey water’ uses within the building.
All existing VERIZON buildings in the Phase One portion of the property received internal environmental abatement and demolition of all existing buildings except a small portion. The remaining portion of the existing buildings were retained and renovated for use by VERIZON, this building is located adjacent to the new three story NATIONAL GRID Headquarters structure.
New off-site traffic improvements included major expansion of traffic capacity and new turning lanes along Winter Street along the Cambridge Reservoir and the main entrance into the new office campus.
For the Phase Two redevelopment of the overall campus an additional three story office building is planned supported by an increased parking garage structure; a new hotel site is also anticipated.
Project Status: The property was purchased in partnership between Davis Marcus Partners (Developer) and Prudential Real Estate Investors (Equity Partner) to create a world-class headquarters campus. The first phase of redevelopment, a 312,000 square foot office complex and new six-story parking garage was delivered using ‘Fast-track GMP’ procedures with the project scheduled for delivery within a demanding thirteen month period (‘Core & Shell’ delivered in February 2009).
​
Project Design-Construction-Credits:
Office Headquarters Redevelopment – Phase One / NATIONAL GRID:
Developer: Davis Marcus Partners
Owner: DMP RWE II, LLC
Equity Partner: Prudential Real Estate Investors
Equity 3rd Party: GDHarley & Associates, Inc.
Lender: Wachovia Bank, NA
Contractor/CM: John Moriarty & Associates, Inc.
Architect-Base
Building: ADD Inc.
Geotechnical Engineer: Sanborn, Head & Associates
Structural Engineer: McNamara / Salvia, Inc.
MEP Engineer: AHA Consulting Engineers
Specifications: Kalin Associates, Inc.
Civil Engineers: John Crowe Associates
Landscape Architect: Geller Devellis Associates
Owner’s Materials
Testing Consultant: UTS of Massachusetts
Tenant’s Architect: Sasaki Associates
Tenant’s Consultants:
Construction Manager: John Moriarty & Associates, Inc.
Development Manager: Jones Land LaSalle
MEP Engineer: AHA Consulting Engineers
Lighting Consultant: Atelier Ten
Acoustical Consultant: Cavanaugh Tocci Associates, Inc.
Specifications: Kalin Associates, Inc.
Audio-Visual: ACT Associates
Telecommunications: CCR Pyramid, Inc.
Solar Design: Solar Design Associates, Inc.
Brief Project Technical Description – Phase One / NATIONAL GRID:
-
New Parking Garage was constructed of precast concrete components, total parking is 420 spaces, garage façade features expanded stainless steel fabric mesh as part of design and initial garage allows for future expansion in support of the overall campus development.
-
Headquarter building for NATIONAL GRID gained 1st Platinum Certified Core and Shell building in the Commonwealth of Massachusetts – NATIONAL GRID’s tenant improvements also achieved the LEED GOLD Certification.
-
NATIONAL GRID added other energy conservation features to the building including solar electrical (Photovoltaic) panels on the building’s roof; the PV Solar system included (736) solar panels producing about 25 kW (DC) electricity – two inverters will convert the DC power to AC for use within the building.
-
The building also features solar shading louvers on the south facing facades thereby controlling solar overheating of interior spaces; all roof rain water is also stored in a large storage tank under the building for use in landscape irrigation and ‘grey water’ uses within the building.
-
Storm water drainage detention pond excavations required removal of existing outcroppings & stone ledge.
-
Site work improvements included renovated and new parking lots connected by sidewalks to entrance atrium, new storm drainage system including controlled retention structures, renovated fire protection system, supplemental new driveways and plazas, new electrical services and site lighting and extensive new landscaping.
National Grid Regional Headquarters